Lake Turkana Wind Power project on course to meet 2017 deadline

 

The Lake Turkana Wind Power project has achieved a new milestone, having installed 155 turbines of 365 turbines in the past six months. The 310 MW turbines, which are attached to 52 meter rotors are hoisted on towers stretching up to 44 meters high across the arid Sarima Village, in Marsabit County. Once completed, the project will be the largest wind farm in Africa

“By managing to hoist these turbines within the stipulated time, the team has not only achieved a technological feat, but also navigated through a logistical challenge of getting all the turbines here in Loiyangalani, which is 1200 KM from the port of Mombasa. This is a clear demonstration that we are on course to launching the largest wind farm in Africa on time,” said Lake Turkana Wind Power General Manager, Phylip Leferink.

The company states that the Vestas turbines are already being tested for power generation. Lake Turkana Wind Power is expected to complete the installation process by June 2017 with a turbine being installed daily. The assembly of the turbines began in March 2016 after the civil works on the foundations of the first batch of turbines had been completed. The various parts, including the blades were transported by road to the site from the port of Mombasa.

The turbine technology is of Danish origin but the production of the turbines, blades and towers was done in the Vestas manufacturing facilities in China.

“We are impressed with the progress that we have made so far; we are working with our project partners to ensure that we complete this wind farm within the stipulated time. This will ensure that we will soon be able to play a key role in Kenya’s energy supply and make a significant contribution towards the country’s economic growth,” Leferink explained.

The firm targets to inject the first 90 MW of wind power into the national grid by the second quarter of 2017. When operating at full capacity, Lake Turkana Wind Power will add 310 MW of renewable generation capacity to Kenya’s grid. This output from the wind farm will be enough to power more than 1 million Kenyan households.

The Marsabit-based wind firm has a 20-year deal to sell electricity at Sh8.6 per kilowatt/hour (kWh) to Kenya Power. The farm sits on 40,000 acres of land in an area that receives steady winds throughout the year.

The power will be evacuated and transmitted to the national grid through a double circuit 400kV, 438km transmission line that is currently being constructed by Kenya Electricity Transmission Company (Ketraco). Kenya, which relies heavily on renewables such as geothermal and hydro-power, aims to expand installed capacity to about 6,700 MW by 2017, up from 1,700 MW in 2013.

 

Previous Standard & Poor’s lowers Kenya’s credit rating outlook from stable to negative
Next Uhuru urges African leaders to combat piracy, terrorism, drug trafficking as governments move to sign maritime security charter

You might also like

Latest 0 Comments

National Bank shareholders approve alternative sources of capital, decry delay of rights issue

 National Bank (NBK) shareholders have approved a request by the lender’s management to turn to other sources of capital, including sourcing debt from international funds and partners. The move follows

News 0 Comments

Top stories from X News global partners

The Guardian UK must pay for Brexit or EU is in ‘deep trouble’, says German minister: German economy minister Sigmar Gabriel has said that Britain must not be allowed to

News highlights- February 27 2017 Wamathai sworn in as Nyeri Governor

Wamathai sworn in as Nyeri Governor Nyeri Deputy Governor Samuel Wamathai was on Monday, 27 February sworn as Governor following the death of Nderitu Gachagua. The swearing in ceremony took

0 Comments

No Comments Yet!

You can be first to comment this post!

Leave a Reply